building permits



Application for Building Permits, called Izin Mendirikan Bangunan (IMB or 1MB) are made to the Head of the Department of Public Works in the area’s Regency / Municipality ‘Dinas PU Kabupaten / Kota’.

The Public Notary can handle this process, and the following documents will be needed for application:
  1. A copy of the location’s zoning permit
  2. A copy of the identity card of the applicant
  3. A copy of the land’s title / official certificate
  4. A copy of the receipt for the land and latest building tax payment record
If the audit appraisal is successful, the Head of the Dinas PU Kabupaten / Kota will issue the, Izin Mendirikan Bangunan (IMB) or Building Permit

Example of costs for ascertaining building permits and major utilities

No

Procedure

Av. Time

Est. Cost

Name of Agency

1

Request Pre-approval letter from Zoning Department

1 day

IDR 1,482,000

Local Administrative Zoning Office

2

Receive inspection from Zoning Department

1 day

no charge

Local Administrative Zoning Office

3

Obtain Pre-approval letter from Zoning Department

20 days

no charge

Local Administrative Zoning Office

4

Request and obtain notarized copy of Land Ownership certificate

1 day

IDR 25,000

Notary

5

Preparation of Environmental Management Plan (UKL) and Environmental Monitoring Plan (UPL)

8 days

IDR 15,000,000

Zoning and Road Construction Division

6

Approval for the Environmental Management Plan (UKL) and Environmental Monitoring Plan (UPL)

10 days

no charge

Regional Environmental Control Agency (BPLHD)

7

Request and obtain building construction permit (IMB)

21 days

IDR 9,104,200

Building Permit Office

8

Request and obtain the building completion and compliance minutes

28 days

IDR 62,500

Land and Building Tax Office

9

Obtain building usage permit (IPB)

49 days

no charge

City Planning Office

10

Register with land and building tax office

11 days

no charge

Land and Building Tax Office

11

Obtain electricity connection

8 days

IDR 12,500,000

Perusahaan Listrik Negara, PT

12

Obtain water and sewerage connection

8 days

IDR 2,000,000

PAM

13

Obtain phone connection

4 days

IDR 500,000

PT. Telekomunikasi Indonesia

 

Estimated total costs including installation of major utilities:

IDR 40,611,200

 